You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?
- Communicate why the change request was rejected and record the results in the lessons learned documentation for your program.
- Inform the stakeholders that their change requests have been rejected.
- Communicate the change request status to the stakeholders and record the results of the change request in the change register.
- Inform the stakeholders why their change requests have been rejected.