You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?

Last Updated on March 27, 2022 by Admin 3

You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?

  • Mitigation
  • Sharing 
  • Acceptance
  • Transference