A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:
– Coordinate project schedule
– Manage to the triple constraint
– Provide performance feedback to team members’ managers
Which of the following types of organizational structures did the new project manager MOST likely join?
- Balanced matrix
- Strong matrix
- Functional