Last Updated on August 11, 2021 by Admin 3
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
- Compromising
- Smoothing
- Withdrawing
- Accepting