Which of the following processes is described in the statement below?

Last Updated on March 27, 2022 by Admin 3

Which of the following processes is described in the statement below? “It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project.”

  • Monitor and Control Risks 
  • Identify Risks
  • Perform Qualitative Risk Analysis
  • Perform Quantitative Risk Analysis
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments