Which of the following is used for breaking down a project into easily manageable components or bites?

Last Updated on February 12, 2022 by Admin 2

Which of the following is used for breaking down a project into easily manageable components or bites?

  • Activity list
  • RBS
  • WBS
  • Contract
Explanation:
Answer option C is correct.
Chapter: Project Charter and Scope Management