Which of the following is the MOST critical step in planning an audit?

Last Updated on December 25, 2021 by Admin 3

Which of the following is the MOST critical step in planning an audit?

  • Implementing a prescribed auditing framework such as COBIT
  • Identifying current controls
  • Identifying high-risk audit targets
  • Testing controls
Explanation:​
In planning an audit, the most critical step is identifying the areas of high risk.