Which of the following is the appropriate ordering of the critical path?

Last Updated on August 11, 2021 by Admin 3

A project has activities on the critical path that must be completed before other activities can start.

Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.

Which of the following is the appropriate ordering of the critical path?

  • B, A, D
  • C, B, D, A
  • D, A, C
  • B, C, A, D