Which of the following is an output of the Perform Integrated Change Control process?

Last Updated on March 28, 2022 by Admin 2

Which of the following is an output of the Perform Integrated Change Control process?

  • Cost-benefit analysis
  • Updated project charter
  • Approved change request
  • Multicriteria decision analysis