Where should the project manager record the issue, and why?

Last Updated on April 19, 2022 by Admin 3

The project’s change control approach states that PRINCE2’s recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials and marketing channels be introduced to support the launch of the training course. The senior user has suggested that this should be managed informally.

Where should the project manager record the issue, and why?

  • In the daily log, because a change to a product at the default level can be handled informally.
  • In the daily log, because the senior user has advised that this change should be informally.
  • In the issue register, because this is a request for change requiring a change to a baseline.
  • In the issue register, because issues should be recorded here first, before determining how to manage them.