What should the program manager do to address the situation?

Last Updated on March 31, 2022 by Admin 2

During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.

What should the program manager do to address the situation?

  • Review and update the detailed stakeholder list.
  • Review and update the stakeholder engagement plan.
  • Execute the component project’s communications management plan.
  • Update the risk register.