Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?

Last Updated on August 11, 2021 by Admin 3

A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?

  • Wait until the change requests are approved by the CCB.
  • Approve the changes because the additional functionality is required to complete the process.
  • Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
  • Schedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments