There are not enough resources available to add the additional audit to the schedule. Which of the following is the BEST course of action?

Last Updated on December 14, 2021 by Admin 3

An audit team has a completed schedule approved by the audit committee. After starting some of the scheduled audits, executive management asked the team to immediately audit an additional process. There are not enough resources available to add the additional audit to the schedule. Which of the following is the BEST course of action?

  • Revise the scope of scheduled audits.
  • Propose a revised audit schedule.
  • Approve overtime work to ensure the audit is completed.
  • Consider scheduling the audit for the next period.