The free float for Activity E is how many days?

Last Updated on March 26, 2022 by Admin 2

The following is a network diagram for a project.

CAPM Certified Associate in Project Management (PMI-100) Part 09 Q04 004
CAPM Certified Associate in Project Management (PMI-100) Part 09 Q04 004

The free float for Activity E is how many days?

  • 2
  • 3
  • 5
  • 8