Last Updated on April 30, 2022 by Admin 3
PRINCE2 RR : Re-Registration : Part 10
-
Identify the missing words in the following sentence: The six aspects of project performance to be managed are [?] costs, timescales and scope,
- benefits, progress, risk,
- benefits, quality, risk,
- change, quality, progress,
- benefits, customers, quality,
-
Which is a type of issue?
- A lesson
- A request for change
- An Exception Report
- A risk with an estimated high impact
-
Which is part of the PRINCE2 definition of a project?
- An undertaking that consists of at least two management stages
- A description of what must be delivered in order to gain acceptance
- The total of a plan’s products
- A temporary organization that is created for the purpose of delivering business products
-
Which is a responsibility of a Team Manager?
- Producing Highlight Reports for the Project Manager
- Reviewing the status of the stage
- Setting Work Package tolerances
- Ensuring delivery of products in the Managing Product Delivery process
-
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
- Progress
- Change
- Organization
- Quality
-
What do acceptance criteria identify?
- The approach that will be used to prove whether the project’s products have been completed
- A measureable improvement resulting from a project outcome
- The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
- The project controls set up during the process Initiating a Project
-
Identify the missing word in the following sentence: A purpose of the [?] theme is to control any unacceptable deviations from the project’s objectives.
- Change
- Plans
- Progress
- Risk
-
Which is a purpose of a Lessons Report?
- Improve the project management method for future projects
- Detail open issues and risks that need to be managed after the project has closed
- Compare the actual performance of the final stage against its plan
- Provide a summary of the benefits realized during the project
-
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.
- change budget
- cost tolerance
- risk budget
- scope tolerance
-
How is a Benefits Review Plan used in the Closing a Project process?
- Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
- To capture the baseline measures against which to assess benefits
- To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
- To gain approval for the post-project activities and transfer responsibility to corporate or programme management
-
Which is a task of product-based planning?
- Design the plan
- Create the product flow diagram
- Analyze the risks
- Prepare the schedule
-
Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,
- Progress
- Plans
- Organization
- Business Case
-
Which is shown in a product breakdown structure?
- Management stages, major products and control points
- In which order the products should be created
- The major products that are to be developed in a plan
- What resources are required to develop the products
-
Which is a purpose of the Project Product Description?
- Define the key responsibilities for delivering product quality
- Provide information about the state of products
- Define the quality anticipated by the customer
- Provide product cost input to the Business Case
-
Identify the missing words in the following sentence. An objective of the Directing a Project process is to [?] throughout a project’s life,
- document how risks will be managed
- identify who will be responsible for quality
- provide management direction and control
- define the benefits to be realized
-
Which is a benefit of using PRINCE2?
- Is a method specifically designed for technical projects
- Provides for the efficient and economic use of management time
- Includes many of the proven planning techniques, such as critical path analysis
- Can be used to manage both projects and programmes
-
Which statement describes the responsibilities of a risk actioned?
- Identifying risks to the project that might occur in their department
- Owning and authorizing the use of the risk budget to fund risk responses
- Managing, monitoring and controlling of all aspects of an assigned risk
- Carrying out a risk response action to respond to a particular risk
-
Which is a purpose of the Managing Product Delivery process?
- Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
- Provide a controlled link between the Project Manager and the Team Manager(s)
- Enable the Project Board to request updates to the current Team Plan
- Establish solid foundations for the project
-
Which role is responsible for specifying the project benefits?
- Corporate or programme management
- Executive
- Senior User(s)
- Project Manager
-
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,
- producing an achievable Project Plan
- preventing poorly-conceived projects from ever being initiated
- obtaining approval from all stakeholders
- setting up the required project controls