Last Updated on March 19, 2022 by Admin 3

PRINCE2 RR : Re-Registration : Part 09

  1. If an informal issue is defined as a problem or concern, where should it first be recorded?

    • Issue Register
    • Risk Register
    • Daily Log
    • Exception Report
  2. Which may be funded from a risk budget?

    • Corrections due to off-specifications
    • Impact analysis of requests for change
    • Implementation of a fallback plan
    • Preparation of the Risk Management Strategy
  3. Which of the following statements about lines of authority and reporting are true?

    1. The Project Manager has day-to-day control for a management stage within the limits laid,
    2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.

    • Only 1 is true
    • Only 2 is true
    • Both 1 and 2 are true
    • Neither 1 or 2 are true
  4. When considering risks, which describes an opportunity in a project?

    • An uncertain event that could have a negative impact on objectives
    • An uncertain event that could have a favourable impact on objectives
    • An event that has occurred resulting in a negative impact on objectives
    • An event that has occurred resulting in a favourable impact on objectives
  5. What is the first task of product-based planning?

    • Produce the Initiation Stage Plan
    • Write the Project Product Description
    • Identify dependencies
    • Create the product breakdown structure
  6. Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

    • Risk category
    • Risk description
    • Risk response
    • Risk status
  7. Which is an objective of the quality review technique?

    • To identify a product’s quality criteria
    • To provide assurance that the project is being conducted properly
    • To assess that a product conforms to set criteria
    • To ensure that staff are properly trained in the quality methods
  8. How many tasks does the product-based planning technique describe?

    • One
    • Two
    • Three
    • Four
  9. Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

    • Principles
    • Processes
    • Tailoring PRINCE2 to the project environment
    • Themes
  10. Which process provides the Project Board with the information it requires in order to commit resources to the project?

    • Managing Product Delivery
    • Initiating a Project
    • Controlling a Stage
    • Directing a Project
  11. Identify the missing word in the following sentence: A project’s output is produced during a project but the [?] for the project are often only realized after the project has closed.

    • costs
    • risks
    • benefits
    • issues
  12. Which should be funded by a change budget?

    • Increase in agreed scope
    • Initiation stage
    • Change Authority
    • Handover activities
  13. What process aims to ensure accurate progress information is provided to the Project Manager?

    • Starting up a Project
    • Managing a Stage Boundary
    • Managing Product Delivery
    • Directing a Project
  14. Which characteristic distinguishes a project from regular business operations?

    • Produces benefits
    • Introduces business change
    • Manages stakeholders
    • Incurs cost
  15. Which of the following describes a use of a Configuration Item Record?

    • Define the identification scheme to be applied to the project
    • Identify the techniques and procedures required within the Work Package
    • Record the change in a product’s status
    • Record the reporting requirements for the Work Package
  16. Which task is performed by the Change Authority?

    • Set a change budget
    • Approve or reject a request for change within approved limits
    • Refer changes that exceed budgetary limits to the Project Manager for approval
    • Update the configuration management system when a change is approved
  17. If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

    • Senior User
    • Executive
    • Corporate/program management
    • Senior Supplier
  18. Identify the missing word(s) in the following sentence: PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,

    • Management strategies
    • Plan
    • Stakeholder interests
    • Time-driven controls
  19. Which is an objective of the Starting up a Project process?

    • Identify who will be responsible for creating the Project Plan
    • Agree how the project will be monitored and controlled after initiation
    • Authorize the Project Manager to proceed with the initiation stage
    • Agree how issues and changes will be identified, assessed and controlled
  20. Which is a purpose of the Risk theme?

    • Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
    • Establish a cost-effective procedure to identify, assess and control uncertainty
    • Establish mechanisms to control any unacceptable deviations from plan
    • Establish mechanisms to manage risks at the corporate or programme level of an organization