If an informal issue is defined as a problem or concern, where should it first be recorded?
- Issue Register
- Risk Register
- Daily Log
- Exception Report
-
Which may be funded from a risk budget?
- Corrections due to off-specifications
- Impact analysis of requests for change
- Implementation of a fallback plan
- Preparation of the Risk Management Strategy
-
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.- Only 1 is true
- Only 2 is true
- Both 1 and 2 are true
- Neither 1 or 2 are true
-
When considering risks, which describes an opportunity in a project?
- An uncertain event that could have a negative impact on objectives
- An uncertain event that could have a favourable impact on objectives
- An event that has occurred resulting in a negative impact on objectives
- An event that has occurred resulting in a favourable impact on objectives
-
What is the first task of product-based planning?
- Produce the Initiation Stage Plan
- Write the Project Product Description
- Identify dependencies
- Create the product breakdown structure
-
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
- Risk category
- Risk description
- Risk response
- Risk status
-
Which is an objective of the quality review technique?
- To identify a product’s quality criteria
- To provide assurance that the project is being conducted properly
- To assess that a product conforms to set criteria
- To ensure that staff are properly trained in the quality methods
-
How many tasks does the product-based planning technique describe?
- One
- Two
- Three
- Four
-
Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?
- Principles
- Processes
- Tailoring PRINCE2 to the project environment
- Themes
-
Which process provides the Project Board with the information it requires in order to commit resources to the project?
- Managing Product Delivery
- Initiating a Project
- Controlling a Stage
- Directing a Project
-
Identify the missing word in the following sentence: A project’s output is produced during a project but the [?] for the project are often only realized after the project has closed.
- costs
- risks
- benefits
- issues
-
Which should be funded by a change budget?
- Increase in agreed scope
- Initiation stage
- Change Authority
- Handover activities
-
What process aims to ensure accurate progress information is provided to the Project Manager?
- Starting up a Project
- Managing a Stage Boundary
- Managing Product Delivery
- Directing a Project
-
Which characteristic distinguishes a project from regular business operations?
- Produces benefits
- Introduces business change
- Manages stakeholders
- Incurs cost
-
Which of the following describes a use of a Configuration Item Record?
- Define the identification scheme to be applied to the project
- Identify the techniques and procedures required within the Work Package
- Record the change in a product’s status
- Record the reporting requirements for the Work Package
-
Which task is performed by the Change Authority?
- Set a change budget
- Approve or reject a request for change within approved limits
- Refer changes that exceed budgetary limits to the Project Manager for approval
- Update the configuration management system when a change is approved
-
If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
- Senior User
- Executive
- Corporate/program management
- Senior Supplier
-
Identify the missing word(s) in the following sentence: PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
- Management strategies
- Plan
- Stakeholder interests
- Time-driven controls
-
Which is an objective of the Starting up a Project process?
- Identify who will be responsible for creating the Project Plan
- Agree how the project will be monitored and controlled after initiation
- Authorize the Project Manager to proceed with the initiation stage
- Agree how issues and changes will be identified, assessed and controlled
-
Which is a purpose of the Risk theme?
- Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
- Establish a cost-effective procedure to identify, assess and control uncertainty
- Establish mechanisms to control any unacceptable deviations from plan
- Establish mechanisms to manage risks at the corporate or programme level of an organization