Which of the following is NOT an event-driven control?
- Project mandate
- Checkpoint Report
- Exception Report
- End of a stage
-
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
- Controlling a Stage
- Closing a Project
- Directing a Project
- Managing a Stage Boundary
-
Which is a type of issue?
- An expected dis-benefit
- An off-specification
- A project outcome
- A scope tolerance
-
Which is a responsibility of a risk owner?
- Identify risks to the project that might occur in their department
- Own and authorize the use of the risk budget to fund risk responses
- Manage, monitor and control all aspects of an assigned risk
- Determine project risk appetite
-
Which is a purpose of a Project Product Description?
- Form part of the Work Package for the project product
- Provide the initial project budget to be refined in the Business Case
- Document the project mandate and gain approval for the project from the Project Board
- Define the quality required of the project’s product
-
Which of the following statements about customer’s quality expectations and acceptance criteria are true?
1.Customer’s quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,- Only 1 is true
- Only 2 is true
- Both 1 and 2 are true
- Neither 1 or 2 are true
-
Which is a purpose of the Controlling a Stage process?
- Produce a Team Plan for the work to be assigned to a Team Manager
- Select and implement actions that will resolve deviations from a plan within tolerance
- Obtain approvals for products delivered in a Work Package
- Update a Project Plan to incorporate the actuals from a Stage Plan
-
Which describes risk impact?
- Timeframe within which the risk might occur
- The trigger that occurred giving rise to the risk
- The effect of the risk on the delivery of project objectives
- How likely the risk is to occur in a given project situation
-
Which statement about stages is true?
- Management stages should be of the same duration
- The use of technical stages is mandatory
- The use of management stages is mandatory
- Management stages are driven by specialist teams
-
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
- Checkpoint Report
- End Stage Report
- End Project Report
- Product Status Account
-
Who represents the three project interests on a project?
- Project Manager
- Project Support
- External project stakeholders
- Project Board
-
Who should act as the communication channel between a project and corporate or programme
management?
- Project Board
- Project Assurance
- Project Manager
- Project Support
-
Where should an off-specification be recorded?
- Risk Register
- Issue Register
- Work Package
- Configuration Management Strategy
-
Why is a Project Brief produced?
- To act as a trigger for the Starting up a Project process
- To record the strategies and management controls to be used by a project
- To provide a full and firm foundation for the initiation of a project
- To be used by the Project Board as a basis for reviewing the progress of a project
-
Which is the purpose of the Change theme?
- Prevent change to baselined products
- Identify, assess and control any potential and approved changes to baselined products
- Establish mechanisms to monitor and compare actual achievements against those planned
- Assess and control uncertainty
-
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,- Only 1 is true
- Only 2 is true
- Both 1 and 2 are true
- Neither 1 or 2 are true
-
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
- the measurement of benefits NOT yet realized
- the handover of products
- open issues and risks
- the release of resources
-
Which should be provided by a project mandate?
- Terms of reference
- Detailed Business Case
- Stage tolerances
- Initiation Stage Plan
-
Which of the following is NOT part of quality planning?
- Define quality responsibilities
- Gain acceptance of the project product
- Agree acceptance criteria
- Set quality tolerances
-
In what process is the authorization to deliver the project’s products given?
- Starting up a Project
- Initiating a Project
- Managing a Stage Boundary
- Directing a Project