Last Updated on March 19, 2022 by Admin 3
PRINCE2 RR : Re-Registration : Part 06
-
Which is NOT a PRINCE2 principle?
- Learn from experience
- Customer/supplier environment
- Defined roles and responsibilities
- Continued business justification
-
Which is NOT a benefit of using PRINCE2?
- Defines specific leadership, motivational skills and other interpersonal skills required
- Can be applied to any type of project
- Promotes learning and continuous improvement
- Defines a thorough but economical structure of reports
-
Which statement applies to Stage Plans?
- Always have the same duration as the Project Plan
- Are produced at the same time as the Project Initiation Documentation
- Assist the Project Manager in the day-to-day running and control of the project
- Provide a baseline against which the Project Board monitor overall progress
-
Which is a purpose of the Directing a Project process?
- Provide the information required to confirm if it is worthwhile to initiate a project
- Enable overall control of a project to be exercised by the Project Board
- Establish the level of control required by the Project Board after initiation
- Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
-
Which describes a risk effect?
- The uncertainty expressed as a negative or favourable occurrence
- The issue which is affecting the project and has resulted in a risk
- The impact(s) on the project objectives should the threat or opportunity occur
- The change in the status of a risk in response to actions taken to control it
-
What is used to identify any organization or interested party who needs to be informed of project closure?
- Configuration Management Strategy
- Project management team structure
- Communication Management Strategy
- Project Brief
-
Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?
- Those that have been completed, but have NOT been quality checked
- Those that have been broken down into sub-products
- Those to be created outside the scope of the project
- Those dependent on more than one other product
-
Which is NOT obtained from a product’s Product Description?
- The product’s quality criteria
- Who will approve the product
- The quality method to be used
- The development method to be used
-
Which is NOT a true statement about the Managing a Stage Boundary process?
- It provides sufficient information for the Project Board to review the success of the current stage
- It is used to create an Exception Plan if requested by the Project Board
- It provides a fixed point at which acceptance of the project product is confirmed
- It is executed at, or close to, the end of each management stage, except the final one
-
In which product would you find a product’s quality tolerance defined?
- Product Description
- Quality Management Strategy
- Quality Register
- Configuration Item Record
-
Which is the Change Authority role permitted to authorize?
- Risks to the project
- Adjustments to the limits on the change budget
- Changes to stage tolerance
- Changes to the project that do not exceed a defined budget
-
Which is an objective of the Initiating a Project process?
- Develop the corporate quality management system as part of the Project Initiation Documentation
- Prepare the plans for the subsequent stages
- Summarize how the organization’s project management method will be tailored for the project
- Request authority from corporate management to deliver the project
-
Which is a purpose of the Quality theme?
- Establish how the project will ensure that all products created meet their requirements
- Establish quality assurance to maintain the quality management system
- Identify all the products of the project to ensure the scope has been adequately defined
- Determine the communication needs of the organization’s quality assurance function
-
Which does the Executive need to ensure is in place before the project is initiated?
- All Work Packages are authorized
- An understanding of how the project will contribute to corporate objectives
- The Project Plan has been approved
- The Project Initiation Documentation is complete
-
Which is NOT one of the levels of plan recommended by PRINCE2?
- Benefits Review Plan
- Project Plan
- Stage Plan
- Team Plan
-
Which is a purpose of a Lessons Log?
- Note any lessons that are raised in Checkpoint Reports
- Record that corrective action is being taken
- Escalate lessons to the Project Board
- Raise improvements with Project Assurance
-
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
- Manage by stages
- Manage by exception
- Continued business justification
- Learn from experience
-
Which role does NOT set tolerances?
- Corporate or programme management
- Project Board
- Change Authority
- Project Manager
-
What theme estimates the cost of delivering the project?
- Business Case
- Change
- Plans
- Progress
-
Which is a purpose of the Directing a Project process?
- Create and authorize the project mandate
- Ensure that work on products allocated to the team is authorized and agreed
- Control the day-to-day running of the project
- Delegate day-to-day management of the project to the Project Manager