Last Updated on March 18, 2022 by Admin 2

PMI-ACP : PMI Agile Certified Practitioner : Part 25

  1. This role champions the products, provides the budget and supports the Scrum Master in removing impediments

    • Subject Matter Expert
    • Product Owner
    • Business Owner
    • Project Manager
  2. The behavior where the Scrum Team focuses on one or more stories until they are done is called:

    • Collaboration
    • Swarming
    • Pair-programming
    • Sprinting
  3. DRAG DROP

    Match the following roles on the right to the RASCI on the left:

    PMI-ACP PMI Agile Certified Practitioner Part 25 Q03 037 Question
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q03 037 Question
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q03 037 Answer
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q03 037 Answer

    Explanation:
    Accountable – Product Owner
    Consulted – Subject Matter Experts
    Informed – Stakeholders & Business Owner
    Supportive – Scrum Master
    Responsible – Team Members
  4. The product owner should spend at least 3 hours per day with the development team?

    • True
    • False
  5. Which role is external to the Scrum Team but provides a skill that does not exist on the Team?

    • Subject Matter Expert
    • Team Member
    • Scrum Master
    • Project Manager
  6. Pick the 3 common Kanban Katas. (Choose three.)

    • Daily Standup Meeting
    • Iteration Demo
    • Improvement Kata
    • Sprint Restrospective
    • Weekly Status
    • Operations Review
  7. Which of the following is NOT considered an enterprise Agile method?

    • DAD
    • XP
    • LeSS
    • SAFe
  8. This Agile methodology’s properties include Focus, Osmotic Communication and Project Safety.

    • Scrum
    • Crystal Clear
    • Extreme Programming
    • Kanban
  9. Which of the following frameworks has the following practices?

    PMI-ACP PMI Agile Certified Practitioner Part 25 Q09​ ​038
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q09​ ​038
    • Dynamic Systems Development Method (DSDM)
    • Crystal Clear
    • Feature Driven Development (FDD)
    • Agile Delivery Framework
  10. Which of the following is NOT a prioritization technique?

    • User Story Mapping
    • Kano analysis
    • Minimally Marketable Features (MMF)
    • Kitchen Prioritization
    • Planning Poker
  11. DRAG DROP

    Sequence the steps to User Story Mapping.

    PMI-ACP PMI Agile Certified Practitioner Part 25 Q11 ​039 Question
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q11 ​039 Question
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q11 ​039 Answer
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q11 ​039 Answer

    Explanation: 
    1. Product Roadmap Definition
    2. User Story Definition
    3. User Story Decomposition
    4. Release Planning
  12. Choose which three statements are true about Approved Iterations: (Choose three.)

    • Meets the definition of Done
    • The Architect has approved it
    • It is communicated to all Team members and stakeholders
    • As a result, the Product Owner updates Roadmaps and Release Plans
    • There is no technical debt
  13. “Fail Sooner” is a benefit of Incremental Development.

    • True
    • False
  14. Non-functional requirements should be written as user stories whenever possible.

    • True
    • False
  15. CRUD is an acronym that defines a way to split stories. What does CRUD stand for?

    • Create/Update/Delete
    • Capture/Replace/Update/Define
    • Create/Review/Update/Done
    • Create/Replace/Update/Define
  16. DRAG DROP

    Match the story types on the left to their definition on the right:

    PMI-ACP PMI Agile Certified Practitioner Part 25 Q16 ​040 Question
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q16 ​040 Question
     
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q16 ​040 Answer
    PMI-ACP PMI Agile Certified Practitioner Part 25 Q16 ​040 Answer
    Explanation: 
    Architecturally Significant – Stories are functional Stories that cause the team to make architectural decisions
    Analysis – Stories that are created to find other stories.
    Infrastructure – Stories to improve the infrastructure the team is using.
    Spike – Stories that figure out answers to tough technical or design problems.
  17. Operations and Maintenance staff should not be part of the Agile team.

    • True
    • False
  18. Which of the following is NOT a metric that measures the performance of DevOps in Agile?

    • Release date adherence percentage
    • Defects attributable to platform/support requirements
    • Percentage of NFRs met
    • Business value realized per release
    • Percentage increase in the number of releases
  19. Which of the following is NOT a KPI (key performance indicator) of Agile?

    • Actual Stories Completed vs. Committed Stories
    • Quality Delivered to Customers
    • Team Enthusiasm
    • Team Attendance
    • Team Velocity
    • Technical Debt Management
  20. Your project management office (PMO) has suggested your project could benefit from self-assessment work at the next retrospective.

    Which of the following benefits would they most likely be looking to achieve from a self-assessment?

    • Assess compatibilities for pair programming assignments
    • Improve personal and team practices
    • Identify personal traits for human resources counseling
    • Gain insights for salary performance reviews