Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations.
As a high-performance team, what should the team do?
- Raise an impediment that resource tasks will be blocked, and notify the product owner
- Ask the delivery manager for a temporary resource
- Ask the scrum master to assign that team member’s tasks to the next available resource
- Assume the team member’s tasks to meet iteration goals, and notify the product owner