  1. A company uses Dynamics 365 Supply Chain Management.

    The company is consistently short on inventory for a group of produced finished good items. This creates customer service issues.

    You need to ensure that production orders are automatically created when inventory is low.

    Which two actions should you perform? Each answer represents a partial solution.

    NOTE: Each correct selection is worth one point.

    • Update the item maximum.
    • Update the item minimum.
    • Set Capable to Promise.
    • Create a safety stock journal.
    • Create a transfer journal.
  2. A company uses planning optimization in Dynamics 365 Supply Chain Management.

    A planning optimization job is triggered by mistake from the user interface. The planning optimization job is running with incorrect runtime filters.

    You need to resolve the issue.

    What should you do?

    • Cancel the job from the plan history.
    • Cancel the job from the dialog box.
    • Disable the environment add-in.
    • Cancel the planning optimization fit analysis.
  3. DRAG DROP

    A company implements Dynamics 365 Supply Chain Management.

    The company needs to improve the reliability of their forecasting data.

    You need to implement demand forecasting to meet the requirements.

    What should you do? To answer, drag the appropriate actions to the correct requirements. Each action may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q03 096 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q03 096 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q03 096 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q03 096 Answer
  4. DRAG DROP

    A company is implementing Dynamics 365 Supply Chain Management.

    You need to determine which planning engine meets each business requirement.

    Which planning engine should you use for each requirement? To answer, drag the appropriate planning engines to the correct requirements. Each planning engine may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q04 097 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q04 097 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q04 097 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q04 097 Answer
  5. DRAG DROP

    A company uses Dynamics 365 Supply Chain Management with master planning.

    The company needs to enable planning optimization functionality to improve master planning processes.

    You need to advise which prerequisites the company must fulfill to enable planning optimization.

    What must the company do? To answer, drag the appropriate types to the correct prerequisites. Each type may be used once, or not at all. You may need to drag the split bar between panes or scroll to view content.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q05 098 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q05 098 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q05 098 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q05 098 Answer
  6. DRAG DROP

    A manufacturing company uses Dynamics 365 Supply Chain Management.

    You must update the safety stock level for raw materials.

    You need to calculate and process minimum coverage proposals based on data from historical transactions.

    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q06 099 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q06 099 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q06 099 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q06 099 Answer
  7. HOTSPOT

    A company implements Dynamics 365 Supply Chain Management.

    You complete the prerequisites to implement the master planning optimization.

    You need to configure the planning optimization feature.

    What should you do? To answer, select the appropriate options in the answer area.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q07 100 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q07 100 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q07 100 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q07 100 Answer
  8. HOTSPOT

    A company that has three legal entities is implementing Dynamics 365 Supply Chain Management.

    One legal entity supplies the other two legal entities as customers with inventory. Intercompany master planning must be set up and run in the least amount of time.

    You need to configure the system to meet the requirements.

    What should you configure? To answer, select the appropriate options in the answer area.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q08 101 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q08 101 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q08 101 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q08 101 Answer
  9. HOTSPOT

    You are configuring the period templates that are used for inventory inquiries. Today’s date is November 3, 2020.

    The period templates configuration is shown in the following graphic. You set the value for the Direction field to backward.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q09 102
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q09 102

    Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q09 103 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q09 103 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q09 103 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q09 103 Answer
  10. HOTSPOT

    A client uses master planning in Dynamics 365 Supply Chain Management.

    The client wants to make sure that the item coverage groups are configured properly.

    You need to validate the configurations.

    Which configurations should you validate for each scenario? To answer, select the appropriate options in the answer area.

    NOTE: Each correct selection is worth one point.

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q10 104 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q10 104 Question
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q10 104 Answer
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q10 104 Answer
  11. This is a case study. Case studies are not timed separately. You can use as much exam time as you would like to complete each case. However, there may be additional case studies and sections on this exam. You must manage your time to ensure that you are able to complete all questions included on this exam in the time provided.

    To answer the questions included in a case study, you will need to reference information that is provided in the case study. Case studies might contain exhibits and other resources that provide more information about the scenario that is described in the case study. Each question is independent of the other questions in this case study.

    At the end of this case study, a review screen will appear. This screen allows you to review your answers and to make changes before you move to the next section of the exam. After you begin a new section, you cannot return to this section.

    To start the case study
    To display the first question in this case study, click the Next button. Use the buttons in the left pane to explore the content of the case study before you answer the questions. Clicking these buttons displays information such as business requirements, existing environment, and problem statements. If the case study has an All Information tab, note that the information displayed is identical to the information displayed on the subsequent tabs. When you are ready to answer a question, click the Question button to return to the question.

    Background

    Best for You Organics Company started as a home-based business. The founders began making handmade soaps and bath products in their kitchen. As sales increased, the business established a production facility and distribution center that supplies three retail stores.

    Soaps and bath products are manufactured in the production facility and are stocked in the warehouse for distribution to the retail stores. Employees at retail stores use mobile point of sale (MPOS) tablet devices to sell the products to customers.

    The company structure is a single legal entity with two sites as shown in the diagram below:

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 105
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 105

    Current environment

    Best for You Organics plans to introduce a new product line of face creams. Each product in the new line uses the same base ingredients but includes a different extract (for example, lime, avocado, kiwi). The marketing department is preparing to introduce the new product line. Minimal inventory will be held in the warehouse.

    The company uses a cloud-based deployment of Dynamics 365 Supply Chain Management to manage finances for all company operations and locations. The company does not use Bill of Materials (BOM) versioning.

    The production and warehouse facility is set up with the following organizational hierarchy:

    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 106
    MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 106

    External customers include:

    – Customer A: a walk-in store customer (business-to-consumer)
    – Customer B: a customer with an existing account (business-to-business)

    External vendors include:

    – Vendor A: a trucking company
    – Vendor B: a raw materials supplier

    Requirements. General

    The new product line must be set up in the system and readily available for sale when the company introduces the product line to the public at an upcoming trade show.

    Requirements. Production

    You must configure the system to produce the new products:

    – Ensure that the warehouse stocks the minimum quantities of raw materials to produce the products.
    – Use a single version per item.
    – Implement FIFO inventory valuation methods.
    – Track raw and finished goods using different General ledger accounts.
    – Use a primary location to determine where to stock product in the warehouse.
    – Configure alternate locations in the warehouse to hold overstock products and refill the primary location as-needed.

    Requirements. Shipments

    You identify the following requirements related to shipping:

    – Ship product to retail stores weekly.
    – Stores require a packing slip to check in merchandise. Drivers require transport documentation and charge per mile to the stores.
    – Shipments to Store1 must be scheduled for Monday, Wednesday, or Friday. Store1 will sometimes pick up their own deliveries when an order is small because they have their own van. – Shipments to Store2 and Store3 must be scheduled for Tuesday or Thursday.
    – You must transmit Advance Shipping Notifications (ASN’s) to the stores prior to deliveries.
    – Set up the system configuration to allow for store transfers.
    – Set up the system so that products may be shipped to the retail stores as bulk orders.
    – Set up the transport providers to deliver products from the warehouse to the retails stores.

    Requirements. Reporting

    Once the new products are available in stores, review 30 days of historical sales data from day-to-day transactions will determine the reorder quantities.

    Set up reporting to allow the product line to be costed and tracked independent of other items.

    Requirements. Pricing and inventory

    You identify the following requirements related to pricing and inventory:

    – Determine the quantity of the new products that can be produced and ready for sale within the first 90 days. Ensure that specialty packaging is on hand for retail sales. The packaging must be shipped directly to the stores from the vendor.
    – Stores must not inventory the packaging materials. Stores must maintain a 30-day supply of specialty packaging materials. Stores must reorder packaging materials as needed.
    – Retail store customers must pay full retail price. Resellers must receive a 10 percent discount off the list price.

    1. HOTSPOT

      You need to configure automatic warehouse inventory replenishment for items.

      How should you complete the setup? To answer, select the appropriate options in the answer area.

      NOTE: Each correct selection is worth one point.

      MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 107 Question
      MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 107 Question
      MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 107 Answer
      MB-330 Microsoft Dynamics 365 Supply Chain Management Part 09 Q11 107 Answer
    2. You need to set up reordering for new items.

      Which two actions should you perform? Each correct answer presents part of the solution.

      NOTE: Each correct selection is worth one point.

      • Create one coverage group for raw materials and one for finished goods.
      • Set the item coverage manual flag on the warehouse to Yes.
      • Create separate coverage groups for raw materials, finished goods, and retail packaging.
      • Set the item coverage manual flag on the warehouse to No.
      • Create one coverage group for retail packaging items and another for items in the warehouse.