Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

Last Updated on March 19, 2022 by Admin 3

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

  • Project costs will increase.
  • The amount of hours a resource can be used will diminish.
  • The project will take longer to complete, but risks will diminish.
  • Project risks will increase.