In which process is the PID reviewed and, if necessary, updated to reflect external factors that may affect the delivery and business justification of the project?
- Starting up a project
- Initiating a project
- Controlling a stage
- Managing a stage boundary
Explanation:
Reference: https://prince2.wiki/management-products/project-initiation-documentation/