Company policy dictates that full backups are taken every Sunday evening, and incremental backups occur Monday through Saturday in the evening. If data loss were to occur on a Thursday before the backup window, which of the following is the number of backup sets that would be needed to retrieve the lost data come Friday morning?

  • 1
  • 2
  • 3
  • 4
  • 5