If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

Last Updated on August 11, 2021 by Admin 3

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

  • The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
  • The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
  • The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
  • The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.