How much capital should the project set aside for the risk contingency reserve?

Last Updated on March 27, 2022 by Admin 3

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

CISSP-ISSMP Information Systems Security Management Professional Part 08 Q12 001
CISSP-ISSMP Information Systems Security Management Professional Part 08 Q12 001

How much capital should the project set aside for the risk contingency reserve?

  • $142,000
  • $232,000
  • $41,750
  • $23,750