Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

Last Updated on August 11, 2021 by Admin 3

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.

PK0-004 Part 06 Q05 003
PK0-004 Part 06 Q05 003

Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

  • Cost
  • Predecessors
  • Lag
  • Durations
  • Resource loading
  • Subtasks
  • Float