For your project archives, which one of the following is an output of risk monitoring and control?

Last Updated on March 27, 2022 by Admin 3

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

  • Quantitative risk analysis
  • Qualitative risk analysis
  • Requested changes 
  • Risk audits