During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.
What should the program manager do?
- Communicate to the program sponsor regarding the additional estimated cost and request a change order.
- Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
- Request that the project manager make the team members work additional hours and not bill the project.
- Talk with the project manager and find ways to reduce hours in another part of the project.