After defining requirements, the project manager would like to validate the developer’s interpretation and understanding of the user’s request. Which of the following would BEST support this objective?

Last Updated on August 9, 2021 by Admin 3

A project manager is working with a software development group to collect and evaluate user stories related to the organization’s internally designed CRM tool. After defining requirements, the project manager would like to validate the developer’s interpretation and understanding of the user’s request. Which of the following would BEST support this objective?

  • Peer review
  • Design review
  • Scrum
  • User acceptance testing
  • Unit testing