Last Updated on August 11, 2021 by Admin 3
A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?
- Accept risk
- Mitigate risk
- Avoid risk
- Exploit risk
Last Updated on August 11, 2021 by Admin 3