A project team member is estimating the cost of an activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
- Bottom-up estimating
- Three-point estimating
- Analogous estimating
- Parametric estimating
Explanation:
Reference: https://pm4id.org/chapter/9-1-estimating-costs/