A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

Last Updated on August 11, 2021 by Admin 3

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

  • Transfer
  • Accept
  • Avoid
  • Mitigate