A program is completed and the expected benefits are realized.
Before executing the transition and closing of the program, what should the program manager do?
- Create a final program report
- Archive documents and lessons learned
- Obtain approval from the program governance board to initiate program closure activities
- Perform administrative and program management information system (PMIS) closure activities