A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?
- Issue log and process diagram
- Resource analysis and Gantt chart
- Stakeholder analysis and communication plan
- Scatter chart and scope analysis