A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

Last Updated on March 28, 2022 by Admin 2

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

  • Finish-to-Finish (FF)
  • Start-to-Finish (SF)
  • Finish-to-Start (FS)
  • Start-to-Start (SS)
Explanation:
Reference: https://en.wikipedia.org/wiki/Dependency_(project_management)